A.艾拓先锋ITIL CHINA

Prince2认证题库连载(四)

91. Why is theProject Plan updated at the end of every stage? D
A. To identifybenefits already achieved
B. To update theProject Brief
C. In order torevise the current Stage Plan
D. To reflectprogress already made

4 H5 o; u  p' V0 i7 s0 u3 I0 B

92. Exception Plancover what period? B
A. From the problemto the end of the current reporting period
B. From the problemto the end of the plan that cannot finish within tolerance
C. The solution ofthe problem
D. The work neededto put the project back within it tolerances


93. Which optionbest describes what is replaced by an Exception Plan? C
A. A Stage Plan
B. The Project Plan
C. A Plan that willno longer finish within the agreed tolerances
D. An ExceptionReport

& k' L$ T9 i+ n' ^2 P/ C) u6 c. \' L

94. Which plancovers the period from when a plan is predicted to exceed it stolerance to theend of that plan? B
A. An ExceptionReport
B. An ExceptionPlan
C. A Problem Plan
D. AnOff-Specification Plan


95. Which one ofthese items listed is an element of a PRINCE 2 Plan? B
A. The ProjectOrganisation
B. Monitoring andcontrol
C. Plan issues
D. CommunicationPlan


96. Which of thefollowing is NOT listed as an element of a PRINCE 2 Plan? D
A. Tolerances
B. Externaldependencies
C. Monitoring andcontrol
D. The impact onthe Business Case


97. Which of thesestatements is TRUE? B
A. All Stage Plansare written in the initiation stage
B. Each Stage Planis produced near the end of the current management stage
C. Each Stage Planis written after one stage ends and before the next one begins
D. Each Stage Planis written at the beginning of its stage

" m# p$ K3 k9 O) [3 N" G

98. When are allStage Plan created? A
A. Near the end ofthe current management stage
B. Toward the endof the initiation stage
C. After one stageends and before the next one begins
D. Each Stage Planis created at the beginning of its stage

+ D" q  m5 O$ b, Y8 |

99. Which of thesestatements is FALSE? D
A. The Project Planis an overview of the total project
B. For each stageidentified in the Project Plan, a Stage Plan is required
C. An ExceptionPlan needs the approval of the Project Board
D. At least oneTeam Plan is needed for every Team Manager

" B$ p6 m1 I1 H# ?

100. Which plan isNOT approved by the Project Board? C
A. The Project Plan
B. The ExceptionPlan
C. A Team Plan
D. A Stage Plan


101. In whichproduct does PRINCE2 look for the identification of the Chair of a QualityReview? B
A. The Project Plan
B. The QualityRegister
C. The QualityManagement Strategy
D. The ProjectInitiation Document