151. Which reportdoes the Project Board receive at a frequency that it dictates? D
A. Exception Report
B. CheckpointReport
C. End stageassessment report
D. Highlight Report
152. Which reportdoes the Project Manager receive on a regular basis? B
A. Highlight Report
B. CheckpointReport
C. Issue Report
D. Exception Report
153. Which reportassesses what went well or badly? D
A. Follow-on ActionRecommendations Report
B. End Stage Report
C. Post ProjectReview Report
D. Lessons Report
154. Which reportreviews how well the project has been managed? B
A. Follow-on ActionRecommendations Report
B. End ProjectReport
C. Post ProjectReview Report
D. Lessons Report
155. Which reportassesses what worked well and what caused problems? B
A. Follow-on ActionRecommendations Report
B. Lessons Report
C. Post ProjectReview Report
D. Exception Report
156. What name isgiven to the permissible deviation from a plan allowed without immediatereporting to the Project Board? D
A. Allowance
B. Contingency
C. Concession
D. Tolerance
157. What occursduring an end stage assessment? D
A. The ProjectManager explains any deviations from the approved plan
B. The End StageReport and the Stage Plan for the next stage are received by the Project Board
C. The risk summaryis checked by the Project Board to ensure that exposure is still acceptable
D. All of the above
158. Which of thesestatements are true? The specific objectives of an end stage assessment are to: B
1. Check that riskresponses for both opportunities and threats are appropriate
2. Verify that theproduct handover was in accordance with the Configuration Management Strategy
3. Review the StagePlan for which the Project Manager is seeking approval
4. Approve anException Report and Exception Plan
A. All are true
B. Only the firstthree
C. Only the secondis true
D. Only the firstand third are true
159. Which of thesestatements are ture/unture? A
The specificobjectives of an end stage assessment are to:
1. Review theLessons Report
2. Review the EndStage Report
3. Review the NextStage Plan
4. Review theBenefits Review Plan
A. All are true
B. Only the firstthree are true
C. The second idtrue
D. Only the firstand third are true
160. Which of thesestatements are true/untrue?B
The specificobjectives of an end stage assessment are to:
1. Verify that the(update) Business Case continues to demonstrate a viable project
2. Review andapprove the (update) Benefits Review Plan
3. Confirm thestrategies and project controls in the (update) Project Initiation Documentationare adequate for the remainder of the project
4. Review a HighlightReport
A. all are true
B. Only the firstthree are true
C. The second isuntrue
D. Only the firstand third are true
161. An exceptionReport is: B
A. A report toprovide progress information to the Project Board
B. A report to theProject Board for the purpose of decision-making
C. A report to theProject Manager for the purpose of decision-making
D. A replacementfor the current Stage Plan
162. An ExceptionPlan is: D
A. A report toprovide progress information to the Project Board
B. A report to theProject Board for the purpose of decision-making
C. A report to theProject Manager for the purpose of decision-making
D. A replacementfor the plan that can no longer finish within agreed tolerance
163. An ExceptionReport is: A
A. A warning fromthe Project Manager to the Project Board
B. A report toprogramme management for the purpose of decision-making
C. A report to theProject Manager for the purpose of decision-making
D. A replacementfor the current Stage Plan
164. Which of thefollowing statements about an Exception Report are correct/incorrect? B
1. Describes aforecast deviation
2. Provides ananalysis of the consequences of the exception
3. Review thetolerances set for the next stage
A. All threestatements are correct
B. The thirdstatement is incorrect
C. The secondstatement is incorrect
D. Only the firststatement is correct
165. When a majordeviation to a Stage Plan is forecast, what contains the Project Manager’sdescription of the deviation, its consequences and list of options? D
A. Project Issue
B. Exception Plan
C. End Stage Report
D. Exception Report
166. What is thename of the product that defines how and when the projects benefits can bemade? D
A. Benefits RealizationPlan
B. Benefits ReviewReport
C. End ProjectReport
D. Benefits ReviewPlan
167. What is thename of the product that advises all those who have provided resources that theproject is coming to an end? A
A. Project closurenotification
B. End ProjectReport
C. Post projectreview
D. Follow-on actionrecommendations
168. What is thename of the product that documents any unfinished business at project close? C
A. Project ClosureNotification
B. Lessons LearnedReport
C. End ProjectReport
D. Post ProjectReview
169. What is thename of the product that reviews how well the project performed against theoriginal Project Initiation Document? C
A. Project ClosureNotification
B. Lessons LearnedReport
C. End ProjectReport
D. Post ProjectReview
170. What doesPRINCE 2 take as the official start of a project? C
A. Receipt of the projectmandate
B. Project Boardappointments
C. Authorizinginitiation
D. Authorizing aproject DevOps
171. Which of thefollowing may be allocated a tolerance? B
A. Quality, scopeand resources
B. Time and Cost
C. Benefits andperformance
D. Cost andperformance
172. Which optionis extracted from the Project Brief to become part of the PID? A
A. ProjectDefinition
B. Tailoring ofPRINCE 2
C. Risk ManagementStrategy
D. Project Plan
173. Which optionis extracted from the Project Brief to become part of the PID?A
A. Project approach
B. Tailoring ofPRINCE 2
C. CommunicationManagement Strategy
D. QualityManagement Strategy
174. Which optionis not part of the PID? C
A. Projectdefinition
B. Project approach
C. Project mandate
D. Project Plan
175. Which optionis part of the PID? C
A. Assumptions
B. Exceptionprocess
C. Risk ManagementStrategy
D. ContingencyPlans
176. Which reportshould contain statements about achievements, expected achievements and actualor potentialproblems? C
A. PID
B. Quality Log
C. Highlight Report
D. Issue Report
177. Which optionbest describes a purpose of the Highlight Report? B
A. Give advancewarning of Quality Review errors
B. Allow theProject Board to manage by exception between end stage assessments
C. Identify projectrisks
D. Give earlywarning of exception situations to programme management
178. Which reportshould contain statements about achievement, expected achievements and actualor potential problems? C
A. ProjectInitiation Documentation
B. Quality Log
C. Highlight Report
D. Issue Report
179. What would bethe correct sequence of these events? D
1. Holding anException Assessment
2. Creating anException Plan
3. Creating anException Report
A. 1,2,3
B. 2,3,1
C. 3,1,2
D. 3,2,1
180. Which documentprovides the basis for all project board decisions that need to be made duringthe project? D
A. Customer’sQuality Expectations
B. Project Brief
C. Project approach
D ProjectInitiation Documentation